Most quarry deals go wrong for one of four reasons: less rock than promised, a permit that cannot do what the buyer needs, land the seller does not fully control, or a market smaller than it looked. Each one leaves a paper trail. Here are the 20 documents that show it, in the order we would ask for them.
Ask for the first eight before you sign a letter of intent. They kill most bad deals early and cheaply.
First round: before a letter of intent
| # | Document | What it tells you |
|---|---|---|
| 1 | Site map with property lines, permit boundary and current pit | Whether the rock you are paying for is inside the permit and the property |
| 2 | State mining / reclamation permit and all amendments | Permitted area, depth, hours, blasting limits, end date |
| 3 | Local zoning approval or special-use permit, with conditions | Truck routes, hours, setbacks, expiry, caps on output |
| 4 | Three to five years of sales by product, tons and price | The real business, not the pitch |
| 5 | Drill logs and lab test results | Whether the rock exists and meets spec |
| 6 | Any reserve report, with date and author | The seller's tonnage claim and how it was built |
| 7 | Title or lease documents for every tract | Who owns the land and the minerals; royalties owed |
| 8 | Customer list with tons by customer | Concentration risk: one DOT job or one plant can be half the volume |
Second round: confirmatory diligence
| # | Document | What it tells you |
|---|---|---|
| 9 | Water discharge and stormwater permits, with monitoring results | Compliance record and pumping limits |
| 10 | Air permit for crushers and plant | Capacity limits, emission controls, renewal dates |
| 11 | Wetlands or stream permits, if any | Areas you cannot mine without new approval |
| 12 | Reclamation plan and bond amount | Final slopes, depth and the cost to close |
| 13 | Blast records and vibration monitoring | Neighbor risk and limits on future blasting |
| 14 | Complaint and violation history (state, local, federal) | Whether neighbors or regulators are a threat to the permit |
| 15 | Equipment list with age, hours and condition | Near-term capital spending |
| 16 | Plant layout and capacity by product | Whether the plant can make what the market wants |
| 17 | Product test reports for DOT approval | Whether the site is on approved-source lists |
| 18 | Stockpile inventory survey (preferably by drone) | Whether book inventory is real — often the first surprise |
| 19 | Employee list, roles, wages and any union agreements | Who is critical to keep |
| 20 | Environmental site assessment (Phase I, and Phase II if needed) | Fuel spills, buried waste, shop contamination |
Check the federal mine record yourself as well; Issue #7 shows how.
Three tips
- Ask for less, not more. A focused list gets answered. A 200-line request list gets delayed. Start with the eight above and add only what the answers raise.
- Read the permit conditions, not just the permit. The limits that matter — hours, depth, truck counts — are buried in the conditions.
- Walk the pit with the drill logs in hand. The face of the pit is the best drill hole you will get.
Get Quarry Intel every week
New quarries, permits and ownership changes across the U.S., read from the federal registry and state notices. Free by email.
Working on a site or a deal?
ShotRock is an independent mining and aggregates consultancy: due diligence, reserves, permitting, quality and drone surveys.
Figures come from public sources (federal mine registry, USGS, state agencies) as of the issue date and are rounded. General information only, not legal, tax, investment or engineering advice for a specific site.